Abstraction from and discharge to groundwater are controlled by the various environmental regulators in England, Wales, Scotland and Ireland. The regulator for England and Wales is the Environment Agency (EA)

The various stages involved in obtaining consent for an open loop scheme in England and Wales are summarised below:

Stage of work EA control process
Drilling boreholes WR32 Consent to drill
Test pumping boreholes WR39 Water Features Survey.
WR32 consent to test pump
Abstraction (final scheme)



Discharge (final scheme)
WR1 Abstraction licence application.
Pumping test and impact assessment report.
Environmental report if required.
Consent to discharge application.
Impact assessment report.